Actual deployments of small cells has lagged behind perhaps ambitious projections for years. The problem is that, given the unique nature of each site and the regulatory process that governs a particular location, it’s difficult to establish a scalable, predictable process. With deployment estimates ranging from $25,000 to $50,000 per small cell, carriers have struggled to develop a one-size-fits-all approach; coupled with regulations that vary from city to city, it can take months of lead up for field work that can be completed in hours or days.

Case in point, Verizon Wireless is currently working with the city of Palo Alto, Calif., to install 92 small cells, 80 on wooden utility poles owned by the city, and 12 on metal street lights, according to a project description received by the city on Jan. 30.