Scotland reworks Fife, Perth and Kinross gigabit tender yet again

Scotland reworks Fife, Perth and Kinross gigabit tender yet again

The Scottish Government (SG) has today confirmed that it will, yet again, rework and enlarge its gigabit broadband build procurement covering Fife, Perth and Kinross. The planned contract is now set to be worth £38.9m (UK public funding) and to target 35,044 premises in communities that are hard to reach (i.e. those that no other gigabit network is going to cover).

Key Points

  • Public funding rises to £38.9m, from £28.55m.
  • Up to 35,044 premises are in scope, from 17,830.
  • The live tender is being scrapped and re-run.

How the Fife, Perth and Kinross Tender Got Here

This one has a fair bit of history behind it, so make yourself comfortable. Some readers will recall that the SG halted its first tender for the area in June 2025, which was trying to find a builder for what was at that point a £43m Project Gigabit roll-out plan for Fife, Perth and Kinross (Lot 4 – Scotland). This had been tipped to help push full fibre (FTTP) out to an estimated 28,441 premises in rural places that are tough to reach. However, the SG said back then that it had stopped the procurement because there had been a big jump in the number of premises already served or now included in commercial build plans across the same patch, which is a nice enough problem to have. Still, it did mean the groundwork for the first procurement no longer held.

A few months later the SG at last started asking for interest in the revised tender, which was first meant to go to procurement in September 2025 but ended up not getting there until February 2026. That revised tender, which formed part of the UK Government’s Project Gigabit programme (as a regional, Type B, contract), was worth £28.55m and set out to reach 17,830 premises in areas that are hard to reach (normally remote rural ones).

Why the Scope Has Nearly Doubled

In an unexpected twist the SG has today said that it has reworked the original plan a second time and has nearly doubled the number of premises it will cover to “up to” 35,044, while also raising the public funding on the table to £38.9 million.

The increase to 35,000 premises is put down to a fall in how much suppliers now plan to build commercially in the area (mirroring wider strains across the market), as well as extra types of premises now falling within the scope of regional Project Gigabit procurements and new premises turning up in the SG’s dataset (e.g. new build homes). To make room for the additional premises, the current procurement is now being scrapped and swapped for a new bidding process, one designed to get as much broadband coverage and investment as possible into Fife, Perth and Kinross. Tom Arthur, Minister for Business and Fair Work, said the new plan will double the number of premises eligible for fresh broadband coverage and will give the region a significant boost.

Another Delay for the Build Timetable

The downside of reworking the original procurement/tender time after time is that it’s likely to throw the expected delivery timescale off by quite a margin. The earlier procurement had tentatively pictured a 4-year build phase finishing by roughly the close of 2030, which now seems more likely to slide back to 2031 or even 2032.

The revised procurement still isn’t out, so the full details aren’t known, but from the start of that phase it’s usual to allow as much as a year before the contract actually goes to a supplier – assuming the SG doesn’t decide to revise it again. This move is also a bit unusual, as Project Gigabit’s contracts are built to be adaptable, so it isn’t always strictly necessary to fully restart a procurement to change its scope. As last time, a number of broadband operators are known to be active in the contract area, among them Openreach, Virgin Media (inc. nexfibre), Hyperoptic, Netomnia, GoFibre, CityFibre and Highland Broadband. But Openreach or GoFibre are probably among the likeliest candidates here, given their current role in Project Gigabit, although GoFibre could struggle without more funding behind it. Similarly, Openreach tends to like Type C (cross-regional) deals more than Type B ones, so it should be interesting to see what comes of it.

Subscribe to our weekly news digest.

Join now and become a part of our fast-growing community.

Invalid Email Address
Thanks for Subscribing!
We'll be sending you our best soon!
Something went wrong, please try again later